ICT Installation

Client: $8 million

Value: Confidential
Role: Client Representative, Project Management, Design Management

Project Summary:

Delivery of a ICT infrastructure—both passive and active systems—for a high-performance 80MW data centre. The project required extensive coordination across multiple disciplines to ensure seamless integration with critical facility systems.

Passive ICT Scope:

$

Structured Cabling System (SCS) and fibre cabling

$

Main Distribution Frames (MDFs) and interconnect rooms

$

Dual-path, fully redundant physical cabling infrastructure

Active ICT Scope:

$

Aggregation racks and virtual servers

$

Copper cabling and FOBOTs

$

5-month integration period with Security, SCADA, BMS contractors, and internal stakeholders

$8M