CAA ENGINEERING SERVICES
Operational Technology
Visual Guidance Docking System (VDGS) Asset Replacement Fleet)
Value
$11.9m
Duration
18mths
Contract Type
D+C
Status
Current
Client: Sydney Airport
Value: $11.9m
Project ID: 14
Role:
– Project Management
Project Summary:
Led the NIGS/VDGS asset renewal program at Sydney Airport for 81 units across terminals, freight and remote bays, where reliability directly affects operations and customer experience. Scope included lifecycle and replacement design, technology assessment, structural and electrical reviews, optimisation of unit and sensor positioning, and a prioritised renewal plan to minimise operational impact.
Key Deliverables
-
Renewal of 81 VDGS units across terminals, freight bays and remote aircraft stands
-
Lifecycle analysis and replacement strategy development
-
Structural and electrical assessments for new unit integration
-
Technology evaluation and optimisation of sensor alignment/positioning
-
Creation of a prioritised renewal program to minimise operational disruption
-
Enhanced reliability and passenger experience outcomes
Site Wide BMS Upgrades
Value
$3m
Duration
18mths
Contract Type
D+C
Status
Closed
Client: Star Casino
Value: $3m
Project ID: 20
Role:
– Project Management
Project Summary:
Upgraded a 15-year-old Honeywell BMS to the latest EBI platform, including 21 new BMS panels, over 6,000 control points, migration to a converged ICT network and redesigned graphics with a COP analysis tool to modernise control and integration.
Key Deliverables
-
Replacement of legacy BMS with Honeywell EBI platform
-
Installation of 21 new BMS panels and integration of 6,000+ control points
-
Migration of BMS architecture to converged ICT networks
-
Development of new control graphics and implementation of COP analysis tool
-
Improved visibility, control, efficiency and system integration
SCADA / Energy Management System Installation
Value
$3m
Duration
18mths
Contract Type
D+C
Status
Closed
Client: Star Casino
Value: $3m
Project ID: 21
Role:
– Project Management
Project Summary:
Implemented a Schneider EcoStruxure SCADA and Energy Management System to optimise load control across a complex multi-building precinct, including site-wide HV/LV load analysis, a new load-shedding table, 20 PLC boards and integration with existing electrical and mechanical systems.
Key Deliverables
-
Deployment of Schneider EcoStruxure SCADA and EMS
-
HV/LV load analysis across a multi-building campus
-
Development of new load-shedding control tables
-
Installation of 20 PLC boards to enable granular control
-
Integration with existing mechanical and electrical systems
-
Enhanced demand management and operational resilience
Energy Analytics Platform
Value
$0.4m
Duration
6mths
Contract Type
D+C
Status
Closed
Client: Star Casino
Value: $0.4m
Project ID: 27
Role:
– Project Management
-Design Coordination
Project Summary:
Deployed an advanced energy analytics solution integrated with IT and OT, providing near real-time monitoring and reporting. Delivered secure remote access via the converged ICT network, integration of Honeywell/Schneider/Bueno platforms, 6-minute data cycles, and enhanced fault diagnostics, energy insights and monthly reporting.
Key Deliverables
-
Implementation of advanced IT/OT-integrated energy analytics platform
-
Secure remote access via converged ICT network
-
Integration with Honeywell, Schneider and Bueno systems
-
Near real-time energy data (6-minute intervals) for improved insight
-
Enhanced diagnostics to support maintenance and operational decision-making
-
Monthly reporting and performance tracking capabilities
